Q39. Your project uses process orders for the production of liquid chemicals.
What can you define to ensure that production flow only happens in suitable physically connected tanks? Note: There are 2 correct answers to this question.

 
 
 
 

Q40. Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?
Note: There are 2 correct answers to this question

 
 
 
 

Q41. For production orders, cost object controlling (COC) can be carried out on an order-related or product- related basis. Which of the following do you have to consider?
Note: There are 2 correct answers to this question.

 
 
 
 

Q42. Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers to this question.

 
 
 
 

Q43. What does a line hierarchy in repetitive manufacturing represent?

 
 
 
 

Q44. Which stard item categories can you select inside a bill of material (BOM)? Note: There are 2 correct answers to this question.

 
 
 
 

Q45. You want to trigger in-house production of a semi-finished material before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

 
 
 
 

Q46. You want to reduce planning efforts for B and C materials. Which planning procedure do you recommend?

 
 
 
 

Q47. In the Capacity Scheduling Table, which settings can you select for the planning strategy?
Note: There are 3 correct answers to this question.

 
 
 
 
 

Q48. For a production version to be valid consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.

 
 
 
 
 

Q49. What are the key features of using a low level code? Note: There are 2 correct answers to this question.

 
 
 
 

Q50. Which of the following processes lead to an entry in the MRP planning file?
Note: There are 2 correct answers to this question.

 
 
 
 

Q51. If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

 
 
 
 

Q52. You use planning strategy Finite Scheduling with Reverse want to allow scheduling in the past. How can you parameterize this in the strategy profile?

 
 
 
 

Q53. You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.

 
 
 
 

Q54. During production order creation several valid production versions are found. How does the system choose the production version?

 
 
 
 

Q55. Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA.
When can you use mode selection?

 
 
 
 

SAP C-TS422-2023 Exam Syllabus Topics:

Topic Details
Topic 1
  • Lean Manufacturing in SAP S
  • 4HANA: This section covers repetitive manufacturing master data, line load planning, and Kanban systems.
Topic 2
  • Capacity Planning in SAP S
  • 4HANA: This section covers a discussion of SAP S
  • 4HANA best practices, SAP HANA database concept, SAP Fiori user experience, and embedded analytics capabilities.
Topic 3
  • Introduction to SAP S
  • 4HANA Supply Chain Planning: This part covers the background and motivation for SAP S
  • 4HANA, its main components, business applications, and user experience strategy.
Topic 4
  • Introduction to SAP S
  • 4HANA Production Planning: This section covers an overview of production planning components, functions, and planning approaches. Exploration of emerging trends.
Topic 5
  • Advanced Planning in SAP S
  • 4HANA: This section includes an overview of advanced planning fundamentals and master data. Explanation of key tools and processes. Discussion of planning evaluation concepts.
Topic 6
  • Material Requirements Planning in SAP S
  • 4HANA: This part of the exam covers an examination of planning strategies, tools, and long-term planning concepts. Overview of MRP fundamentals and lot size procedures.

 

C-TS422-2023 Real Valid Brain Dumps With 82 Questions: https://www.examboosts.com/SAP/C-TS422-2023-practice-exam-dumps.html

         

Related Links: www.stes.tyc.edu.tw fortunetelleroracle.com www.stes.tyc.edu.tw www.stes.tyc.edu.tw divisionmidway.org www.stes.tyc.edu.tw

 

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below