SAP C_TS412_1909 Certification Exam Topics:

Topic Areas Topic Details, Courses, Books
Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports

Revenues and Payments > 12%

Describe the characteristics of Revenues & Payments.

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Cost and Budgets > 12%

Describe procedures for establishing budgets and reporting costs.

Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones

Material > 12%

Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement

Resources > 12%

Describe how the Resource Planning process integrates with HCM

SAP C_TS412_1909 Exam Description:

The “SAP Certified Application Associate – SAP S/4HANA Project Systems” certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

C_TS412_1909 Exam Certification Details:

Cut Score: 51%
Duration: 180 mins
Languages: English
Sample Questions: SAP C_TS412_1909 Exam Sample Question
Level: Associate

 

NEW QUESTION 47
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

 
 
 
 

NEW QUESTION 48
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

 
 
 
 
 

NEW QUESTION 49
Which planning method can prevent further rescheduling of activities?

 
 
 
 

NEW QUESTION 50
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NEW QUESTION 51
What could be a reason to use expert mode in the valuation method for results analysis?

 
 
 
 

NEW QUESTION 52
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 53
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 54
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

 
 
 
 

NEW QUESTION 55
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question

 
 
 
 
 

NEW QUESTION 56
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

 
 
 
 
 

NEW QUESTION 57
Where can you define a network as “header-account-assigned” or “activity-account-assigned”?

 
 
 
 

NEW QUESTION 58
Which object is used to allocate the costs from a claim to the project structure?

 
 
 
 

NEW QUESTION 59
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.

 
 
 
 
 

NEW QUESTION 60
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

 
 
 
 

NEW QUESTION 61
Which object is relevant in assembly processing to create an assembly order for the SD document?

 
 
 
 

NEW QUESTION 62
To which object can you assign a factory calendar?

 
 
 
 

NEW QUESTION 63
What functionality can you perform with activity elements?

 
 
 
 

NEW QUESTION 64
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

 
 
 
 

NEW QUESTION 65
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

 
 
 
 

NEW QUESTION 66
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element

 
 
 
 

Updated SAP C_TS412_1909 Dumps – PDF & Online Engine: https://www.examboosts.com/SAP/C_TS412_1909-practice-exam-dumps.html

         

Related Links: app.parler.com myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw myportal.utt.edu.tt

 

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below